4. Government Primary School Reconstruction and Renovation Project

4.1 Objectives of the Project:

        i) To reconstruct and renovate the dilapidated government primary schools and to supply furniture to 

            those schools;

        ii) To make provision for construction of sanitary latrines and sinking of tube wells for those government 

            primary schools which don't have latrine and tube well facilities.

4.2. Approval Status:

    a) Original : Approved

    b) Revised : Approved

    c) 3rd Revised : Approved

4.3. Implementation Period:             Original             3rd Revised

            a) Date of commencement:     01/07/1994             -

            b) Date of completion:             -                     30/06/2006

4.4. Source of Project Aid : GoB

4.5 Date of Loan Agreement:     -

 

Total

GoB

PA(RPA+DPA)

RPA

DPA

4.6 Project Cost :

     (in lakh taka)

85511.36

85511.36

-

-

-