4.     IDB Assisted Govt. Primary School Project Construction Project (2nd Phase) 

4.1 Objectives of the Project:

    i)   To construct 311  government primary schools; 

    ii)  To supply necessary furniture and teaching materials to the constructed schools;

    iii) To ensure educational environment to the constructed schools; and

    iv) To expand of primary education in the rural areas. 

4.2. Approval Status:

    a) Original : Approved

    b) Revised : -

4.3. Implementation Period :             Original             Revised

            a) Date of commencement:     01/07/2003             -

            b) Date of completion:            30/06/2006              -

4.4. Source of Project Aid : IDB

4.5 Date of Loan Agreement :     08//09/2003

 

Total

GoB

PA(RPA+DPA)

RPA

DPA

4.6 Project Cost :

        (in lakh taka)

6181.50

798.58

5382.92

5382.92

-

 

Go back