4. IDB Assisted Govt. Primary School Project Construction Project (2nd Phase)
4.1 Objectives of the Project:
i) To construct 311 government primary schools;
ii) To supply necessary furniture and teaching materials to the constructed schools;
iii) To ensure educational environment to the constructed schools; and
iv) To expand of primary education in the rural areas.
4.2. Approval Status:
a) Original : Approved
b) Revised : -
4.3. Implementation Period : Original Revised
a) Date of commencement: 01/07/2003 -
b) Date of completion: 30/06/2006 -
4.4. Source of Project Aid : IDB
4.5 Date of Loan Agreement : 08//09/2003
|
|
Total |
GoB |
PA(RPA+DPA) |
RPA |
DPA |
|
4.6
Project Cost (in lakh taka) |
6181.50 |
798.58 |
5382.92 |
5382.92 |
- |