5. 2004-Flood Damage Primary Education Institutions Rehabilitation/Reconstruction Project
5.1 Objectives of the Project:
a) To repair/rehabilitation of 17000 Govt. /Regd. Non-Govt/Community primary schools partly damaged by flood 2004;
b) To reconstruction of 853 Govt. /Regd. Non-Govt/Community primary schools fully damaged by flood 2004; and
c) To supply of furniture to the 853 reconstructed schools.
5.2. Approval Status:
a) Original : Approved
b) Revised : -
5.3. Implementation Period: Original Revised
a) Date of commencement: July 2005 -
b) Date of completion: June 2007 -
5.4. Source of Project Aid : IDA, ID
5.5 Date of Loan Agreement : IDA: 14-11-1997, ID: 14-03-2001
|
|
Total |
GoB |
PA(RPA+DPA) |
RPA |
DPA |
|
5.6 Project Cost : (in lakh taka) |
29917.21 |
5917.68 |
23999.53 |
- |
- |